Project Network Diagram

Project Network Diagram Instructions: Resource: Project Management, Ch. 6 Complete Exercise 8 in Ch. 6 of Project Management. Include the Project Network Diagram to support your response. Format your paper consistent with APA guidelines. Click the Assignment Files tab to submit your assignment. SupportingMaterial:Project Management, Ch. 6

You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 15 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days.

Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?

image

Needs help with similar assignment?

We are available 24x7 to deliver the best services and assignment ready within 3-4 hours? Order a custom-written, plagiarism-free paper

Get Answer Over WhatsApp Order Paper Now